banner ad
Experts Logo

articles

Acceleration Claims on Engineering and Construction Projects

By: Long International, Inc. - Richard Long P.E.
Tel: (303) 972-2443
Email:Long International, Inc.


View Profile on Experts.com.


1. INTRODUCTION

Time is money especially on engineering and construction projects. Because delays in the completion of the project usually result in increased owner, engineer, and contractor costs, the overall time of performance is vital to the financial success of the project. The importance of time is evidenced by the significant role played by CPM schedules, completion dates, and milestones in the bidding and awarding of engineering and construction contracts. The desire to minimize costs and the time of performance often causes the occurrence of acceleration.

This article discusses the following topics:1

  • Types of Acceleration;
  • Key Elements of Acceleration Required by the Courts;
  • Acceleration Claims Outside of the United States;
  • Notice Requirements;
  • The Relevance of the Date When the Time Extension Is Given;
  • Contract Provisions Associated with Acceleration;
  • The Effect of a "No Damage For Delay" Clause on Acceleration;
  • Identifying Acceleration Using the Project Schedules;
  • Documenting Acceleration Evidence; and
  • Acceleration Damages.

2. TYPES OF ACCELERATION

There are three types of acceleration: directed acceleration, constructive acceleration, and voluntary acceleration.

Directed acceleration occurs when the owner or construction manager issues a specific order to its construction contractor under the contract provisions to 1) complete the project earlier than the originally scheduled completion date, 2) re-sequence the work and/or utilize overtime, additional shifts, and/or extra engineering or construction labor, supervision, or equipment to complete the base contract work plus additional or changed work within the original contract time,2 or 3) re-sequence the work and/or utilize overtime, additional shifts, and/or extra engineering or construction labor, supervision, or equipment to make-up for contractor-caused delays that threaten the on-time completion of the project. These measures can result in costs being incurred that would not otherwise have been required.

. . .Continue to read rest of article (PDF).


Long International provides expert claims analysis, dispute resolution, and project management services to the Process Plant Engineering and Construction industry worldwide. Our primary focus is on petroleum refining, petrochemical, chemical, oil and gas production, mining/mineral processing, power, cogeneration, and other process plant and industrial projects. We also have extensive experience in hospital, commercial and industrial building, pipeline, wastewater, highway and transit, heavy civil, microchip manufacturing, and airport projects.

©Copyright - All Rights Reserved

DO NOT REPRODUCE WITHOUT WRITTEN PERMISSION BY AUTHOR.

Related articles

Dennis-Dunville-Overhead-Crane-Expert-Photo.jpg

5/10/2016· Construction

Lawyers Guide to Cranes: Crane Identification

By: D. Larry Dunville

It is absolutely critical in the evaluation of a legal case involving cranes, to determine what type crane is involved. The word "Crane" is a generic term that covers virtually anything that lifts with a hook, but each crane type is a whole different industry with different industry associations (which compile the industry product specifications), different governing specification and different OSHA requirements. As a matter of fact, some cranes don't even have hooks!

Greg-Gerganoff-OSHA-Safety-Expert-Photo.jpg

10/26/2016· Construction

Independent Safety Professionals, Or "It's All Good, I Can Handle It!"

By: Greg Gerganoff

During a recent conversation with a friend who had purchased a small construction company he mentioned in passing that one of his employees had injured his ankle on the job but didn't report it to his work comp carrier as it was a minor incident, no days off work, didn't want his rates to go up, why bother. All is good. Right?

Dennis-Dunville-Overhead-Crane-Expert-Photo.jpg

6/15/2016· Construction

Avoiding the Pitfalls of Crane Installation In a New Building: Following the Specs May Cost You

By: D. Larry Dunville

You have a shiny new building with a shiny new crane and everything looks great. For some reason, though, the crane won't clear the building columns, even though the contractor and the crane manufacturer are saying everything is to spec and it's not their problem. Common sense says somebody is wrong and that somebody should have to pay (because it's going to cost a bundle).

;
Experts.com-No broker Movie Ad

Follow us

linkedin logo youtube logo rss feed logo
;