banner ad
Experts Logo

articles

Construction Claims For Variation in Quantity

By: Long International, Inc. - Richard J. Long
Tel: (303) 972-2443
Email Mr. Long or Mr. Avalon


View Profile on Experts.com.


1. Introduction

A component of a construction claim often relates to the cost, quantity, and quality of the materials that the contractor installed on a project. The contractor frequently purchases these materials and agrees to install the quantities of materials on a unit price basis, i.e., a unit price that includes both the cost of the materials and the cost to install them. The parties may contemplate some minor variations in such quantities from the contract estimate, especially if the engineering documents are not issued "Approved for Construction (AFC)." Even when AFC drawings are issued prior to establishing the contract price, changes may occur which may cause deviations from the approved design which could significantly increase or decrease the required quantities to be installed and the contractor's costs.

Unit price contracts are often used to shorten the overall duration of a project because a detailed design from which final quantity takeoffs can be performed is not necessary to enable a contractor and owner to agree on a contract to perform the construction work. Thus, field construction work can start earlier than would otherwise be required in a traditional engineering, procurement, construction (EPC) contract or design-build contract, where a more precise measure of quantities is necessary to obtain a lump-sum or fixed-price bid from a contractor. Under a unit price contract, a contractor typically buys material, adds a mark-up for overhead and profit, and agrees to perform the work for this unit price. Of prime importance to the contractor is whether its unit prices are sufficient to cover its overhead and other costs if the number of units significantly changes from the estimated quantities used to prepare its bid. If the owner's estimated quantities are higher than the quantities that are actually required, the contractor may have a claim for unrecovered overhead costs and profit.

An owner, often in an effort to realize cost savings as a result of value engineering, may change the design, reduce the quantities specification, and request a credit from the contractor. However, the contractor might not pass on the full savings it achieved from the owner's change, potentially causing a dispute with the owner who is expecting a larger credit.

Contractors also take risks with unit price contracts. The contractor may tactically apply its overhead and profit percentages in an unbalanced manner to items for which it expects large quantity increases as the design matures, thus receiving an additional layer of profit. As stated by one court:

Such a bid, it is explained, is one in which the contractor allocates a disproportionate share of indirect costs and anticipated profit to the unit prices bid for those items on which he anticipates an overrun; the object being to reap over generous profits should the anticipated overruns materialize

Such practices could backfire if the quantities of "over-priced" items do not materially increase or, even worse, decrease as a result of value engineering, thus reducing the contractor's recovery of overhead and profit.

2. VARIATION IN QUANTITY CLAUSES

. . .Continue to read rest of article (PDF).


Long International provides expert claims analysis, dispute resolution, and project management services to the Process Plant Engineering and Construction industry worldwide. Our primary focus is on petroleum refining, petrochemical, chemical, oil and gas production, mining/mineral processing, power, cogeneration, and other process plant and industrial projects. We also have extensive experience in hospital, commercial and industrial building, pipeline, wastewater, highway and transit, heavy civil, microchip manufacturing, and airport projects.

©Copyright - All Rights Reserved

DO NOT REPRODUCE WITHOUT WRITTEN PERMISSION BY AUTHOR.

Related articles

michael-panish-logo.gif

10/13/2015· Construction

Plastic Laminated Products: Fabrication & Installation Problems

By: Michael Panish

This article will discuss plastic laminated products only. Although many other laminated materials are used for residential and commercial applications, plastic laminates are one of the most common products involved in casework claims and personal injuries.

Sanford-Loy-Construction-Defect-Expert-Photo.jpg

3/30/2023· Construction

Construction Management Agency (CMa): Facts Not Fiction

By: Sanford C. Loy

A Construction Management agency (CMa) will administer these bonds for you to make sure they are written by viable and solvent bond companies who are on the government treasury list for approved bond companies.

long-international-logo.jpg

3/12/2018· Construction

Proving the Cause-Effect Linkage

By: Long International

Contractor’s claim submittals and expert reports are often deficient in proving causation, i.e., the cause-effect linkage. These claims generally outline the owner-caused impacts and separately calculate quantum; however, the two are often not linked in any meaningful way. Most claims are settled prior to a decision by a panel, court, or board, and therefore these deficiencies are not made apparent. Yet, a well-prepared claim document which includes a persuasive and accurate causeeffect analysis can greatly improve the contractor’s chances of a successful recovery, either through negotiations or in arbitration/litigation. This analysis is difficult and often costly to prepare, and is therefore not performed in many disputes, which may be the reason why the claims fail.

;
Experts.com-No broker Movie Ad

Follow us

linkedin logo youtube logo rss feed logo
;