banner ad
Experts Logo

articles

The Collapsed As-Built Windows Schedule Analysis Method

By: Long International, Inc. - Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA
Tel: (303) 972-2443
Email:Mr. Avalon


View Profile on Experts.com.


ABSTRACT

The Collapsed As-Built Windows Schedule Analysis (AACE® International Recommended Practice 29R-03, Method Implementation Protocol 3.9) is a modeled, subtractive, multiple-base method. It is a retrospective CPM schedule analysis which is typically used to prove entitlement for compensable delay and assess concurrency of delay within a window of time. The analysis simulates the as-built conditions within a schedule window and then delays are removed from the CPM model. If the forecasted project finish date "collapses" but-for or absent compensable delays, then entitlement for compensable time-related costs can be demonstrated. This article addresses the usage of the Collapsed As-Built Windows protocol and the advantages and disadvantages of the methodology.

1. INTRODUCTION

It is common that an unanticipated event or issue may cause delay and extend the overall completion of a project. It is also common that project stakeholders may dispute the responsibility for a project issue that caused delay and extended the overall completion of a project. A project issue can become contested, cause multiple delays, affect several areas of a project, occur at different points in time, and become intertwined with non-contested issues. To achieve an equitable resolution of a contested project issue that caused delay, it is imperative for an analyst to answer the following basic questions:

  • Who caused the delay?
  • Why did the delay occur?
  • What impact did the delay cause?
  • Where did the delay occur?
  • When did the delay occur?

On large and complex projects, the process of evaluating delay issues is further complicated when the schedule file is comprised of numerous process areas/units, thousands of activities with activity groups spanning many months or years, and multiple critical and near-critical paths. One retrospective forensic schedule analysis that can be used to evaluate concurrency and quantify compensable delay is the Collapsed As-Built schedule analysis method applied on a windows basis (AACE® International Recommended Practice 29R-03, MIP 3.9).

2. THE COLLAPSED AS-BUILT WINDOWS ANALYSIS DEFINED


. . .Continue to read rest of article (PDF).


Long International provides expert claims analysis, dispute resolution, and project management services to the Process Plant Engineering and Construction industry worldwide. Our primary focus is on petroleum refining, petrochemical, chemical, oil and gas production, mining/mineral processing, power, cogeneration, and other process plant and industrial projects. We also have extensive experience in hospital, commercial and industrial building, pipeline, wastewater, highway and transit, heavy civil, microchip manufacturing, and airport projects.

©Copyright - All Rights Reserved

DO NOT REPRODUCE WITHOUT WRITTEN PERMISSION BY AUTHOR.

Related articles

long-international-logo.jpg

7/5/2022· Construction

Assessment Of Problems Associated With Poor Project Management Performance

By: Long International

The purpose of this paper is to provide an explanation of the methodology and resources that Long International uses to arrive at its opinions on allocation of the responsibility for various problems, and the impact of those opinions on the parties’ entitlement to damages or extensions of the time of performance allowed under a Contract.

acorn_logo.gif

4/11/2005· Construction

Things You Can Do To Avoid Conflict In The Design And Construction Of Building Projects

By: William R. Acorn

Introduction: In our first Volume of the Forensic Exchanger, we discussed some of the all too many reasons why HVAC systems fail. If you missed that edition and are interested in that topic e-mail us and we will gladly send it to you. We will follow up with more discussion of that important topic in later editions

long-international-logo.jpg

8/13/2013· Construction

Construction Claims For Variation in Quantity

By: Long International

A component of a construction claim often relates to the cost, quantity, and quality of the materials that the contractor installed on a project. The contractor frequently purchases these materials and agrees to install the quantities of materials on a unit price basis, i.e., a unit price that includes both the cost of the materials and the cost to install them.

;
Experts.com-No broker Movie Ad

Follow us

linkedin logo youtube logo rss feed logo
;