1. INTRODUCTION
In the construction industry, it is largely agreed that overtime work adversely affects labor
productivity. However, there is no universally accepted method for estimating the resulting loss of
productivity, and many of the studies commonly used to estimate such losses have been subject to
criticism by industry experts and the courts.
This article describes a detailed method for estimating productivity losses retrospectively, i.e., after
the hours have been incurred. The proposed method uses the productivity losses from
an MCAA Bulletin published in 2011, in which the MCAA averaged the results from four
well-known overtime studies. Using this method, one applies the MCAA's productivity factors to
the actual hours on a week-by-week, worker-by-worker basis to estimate inefficient hours. Among
its several advantages, the method a relatively time and cost-effective way of providing detailed
results, as it can be used to show the inefficient hours for a given worker or crew, or the
inefficient hours in a given week or timeframe.
The Sections below include a brief introduction to the MCAA Bulletin, a description of the
proposed method including the steps involved with setting up the Excel model, and the advantages
and potential disadvantages of employing this method.
2. THE MCAA BULLETIN
In 2011, the Mechanical Contractors Association of America, Inc. (MCAA) published Bulletin
No. OT1 Revised, titled "How to Estimate the Impacts of Overtime on Labor Productivity."
In its Bulletin, the MCAA did not provide a study based upon new overtime productivity loss
data, but rather it analyzed and summarized the data from four existing studies:1
- "Schedule Overtime Effects on Construction Projects," published by the
Business Roundtable (BRT) in 1980;
- "Overtime and Productivity in Electrical Construction," published by the
National Electrical Contractors Association (NECA) in 1989;
- "Schedule Overtime and Labor Productivity: Quantitative Analysis," published
by Dr. H. Randolph Thomas (Thomas), et al, of Penn State University in 1997;
and
- "Modification Impact Analysis Guide," Publication No. EP 4150-1-3,
published in 1979 by the U.S. Army Corps of Engineers (COE).
Regarding these four studies, the MCAA wrote:
"These studies have been in use in the construction industry for many years and
have been generally accepted as reliable measures of lost productivity due to
unplanned extended overtime. Each has its strengths and weakness, including
criticisms ranging from the use of limited data sources to the withdrawal of
reports from publication. However, the baseline data in any of these studies have
never been proven to be inaccurate. Moreover, the concept that a contractor's
work force becomes less efficient as unplanned extended overtime is worked is
generally recognized and has never been disproved as an underlying fact." 2
The MCAA also cited four cases in which U.S. Courts and Boards acknowledged and/or allowed
the studies to be used as a basis for quantifying productivity losses due to overtime.3
The MCAA then provided a series of charts for each relevant workweek (50 hours per week,
approximately 55 hours per week, 60 hours per week, etc.). Each chart shows the results of the
applicable studies in terms of the Productivity Index as a function of the duration of scheduled
overtime. Between one and four studies were charted, depending upon the workweek.
For example, the chart for the 50-hour workweek includes data from all four studies (BRT,
NECA, Thomas, and COE),4 while the chart for the 84-hour workweek includes data from
NECA's study alone,5 as the other studies did not evaluate the impacts of an 84-hour workweek.
In the balance of its Bulletin, the MCAA provided a table summarizing its results (discussed
below), and explained and gave examples of the prospective application and the retrospective
application of its PIs to estimate productivity loss. While the method proposed in this article is
generally consistent with the simple example of the retrospective application provided in the
Bulletin, it is a far more detailed approach.
3. DESCRIPTION OF THE METHOD
Table 1 below is a recreated version of the MCAA's results table.6 The results indicate that the
Productivity Index (PI),7 and therefore actual worker productivity, decreases both as the weekly
hours increase and as the duration of overtime work is extended. For example, given a 50-hour
workweek, the table indicates that the first week of overtime results in a PI of 0.95, or a 5% loss
of productivity, while the tenth consecutive week of overtime results in a PI of 0.72, or
a 28% loss of productivity. For a 60-hour workweek, the PIs are 0.91 (9% loss) in first week and 0.61 (39% loss) in the tenth week, or more extensive losses than the comparable
50-hour workweeks.
Table 1
Productivity Indices from the MCAA's Bulletin No. OT1 Revised
The method described in this Section applies the PIs (and resulting productivity losses) from the
MCAA's table, Table 1 above, to the actual hours expended by each worker in each week of
a project. Thus, it is a retrospective analysis in which one can quantify not only the total loss
of productive time, but also the lost hours for a given person, in a specific week, or over
a given timeframe.
As a preliminary matter, this author has not, in prior analyses, interpolated between the data
points provided by the MCAA. One might reasonably argue that in the second consecutive week
of overtime, if a worker expended 67 hours, his or her PI may fall between the PI value for the
63-hour workweek (0.84) and the PI value for the 70 to 72-hour workweek (0.80). However,
given that (i) the MCAA does not address such interpolation, and (ii) the studies upon which the
MCAA's values are based do not provide data for say a 67-hour workweek, an analysis that
includes interpolation between data points may (rightly) come under significant criticism.
Therefore, the analysis described below uses ranges that are consistent with the data provided by
the MCAA, e.g.: workweeks between 0 and 49.9 hours are assigned a PI of 1.0 (no productivity
loss); workweeks between 50.0 hours and 53.9 hours use the PIs from the "50 hrs/wk" column;
workweeks between 54.0 hours and 59.9 hours use the PIs from the "54-56 hrs/wk" column; etc.
Table 2 below is excerpted from a larger table in which productivity losses were calculated for
all workers over the entire duration of a project. It shows only John Smith's time over
a six-week period, from the week ending 21 September 2014 (Week 62 of the project) through
the week ending 26 October 2014 (Week 67 of the project).
Table 2
Example Table - Inefficient Hours for One Worker in a Six-Week Period
. . .Continue to read rest of article (PDF).